The hook-up installation refers to lifting the mooring line previously arranged on the sea bed and connecting it with the structure that has arrived at the installation site. The dynamic behavior of the structure can be controlled using several tugboats and, at the same time, proceeds with a hook-up installation using AHTS (Anchor handling tug supply vessels) and ROV (Remotely operated vehicle). The procedure can be planned in various ways depending on the environmental conditions, shape of the structure, number of mooring lines, and mooring method. In this study, an analysis was conducted on the hook-up procedure, which is generally performed during offshore installation work.
4.3 Hook-up Simulation
In this study, a simulation was performed to evaluate the stability of the structure during hook-up installation.
Table 5 lists the main dimensions of the tugboat for station keeping of the structure, and
Fig. 14 shows the arrangement of the tugboat. In the simulation, the analysis was performed for all hook-up procedures (Steps 1—21) for the case where four tugboats were arranged (Tug 4). For two tugboats (Tug 2) and no tugboat (Tug 0), the analysis was performed from Step 6, where four mooring lines were connected and adjusted to designed pre-tension, to Step 21.
Figs. 15,
–
17 show the
x,
y offset of the structure and the rotational direction
θz on the
x −
y plane in Step 1, which is the step of maintaining the position only with the thrust of four tugboats without connecting mooring lines. First, the structure shows large movement in the
x-direction after 2,250 s have passed (as shown in
Fig. 15). To determine the cause,
Fig. 18 shows the time history of the second-order wave force, which confirmed that more than 300 t of wave force was acting before the large behavior of the structure occurred. As shown in
Table 5, the maximum thrust of one tugboat is 100 t, and the upper limit of the total thrust of a tugboat that can be produced in one direction is 200 t. In other words, due to the limit of the total thrust of the tugboat, the large motion of the structure occurred by the second-order wave force. The behavior in the
y-direction and
θz -direction is a result of the current and wind forces acting on the structure in different directions, suggesting that the offset of the structure is well maintained with only the thrust of the four tugboats.
Figs. 19,
–
21 present the
x,
y, and
θz offset of the structure in Step 6, which is connected with four mooring lines by designed pre-tension. Each graph compares the behavior of the structure according to the number of tugboats. Tug 4 has four tugboats with mooring lines; Tug 2 has two tugboats with mooring lines; Tug 0 has no tugboat with connecting mooring lines only. First, the analysis of the time history of the
x-direction offset resulted in stronger behavior when there were two tugs than when there were four tugs. When there was no tugboat, large motion of the structure occurred at a distance away from the origin due to the steady drift force.
Among the external forces acting on the structure, the wave force is dominant. To control it, the tugboat generates an excessive force in the x-direction. The thrust in the x-direction of the tugboat causes a rotational moment in the structure. To control the y-direction offset of the structure due to the rotational moment, the tugboat produces a moment in the opposite direction by generating thrust. Therefore, when maintaining the position of the structure using two tugboats, the offset of the structure is larger in the case of the y-direction and θz -direction than the other cases. Therefore, the offset of the structure without connecting the tugboat converges to the point away from the origin and returns to the origin when using four tugboats. In other words, if two tugboats are used in Step 6, the x offset of the structure can be controlled, but and θz offset appears unstable. In addition, when the tugboat is not connected, the offset of the structure deviates from the origin due to the steady drift force, causing instability. Therefore, it is important to maintain the position of the structure using four tugboats in this step.
And in the situation where two tug boats were arranged, the structure shows larger amplitudes in the y and θz directions than other cases, but was relatively stable compared to Step 6.
Figs. 22,
–
24 show the
x,
y, and
θz offset of the structure in Step 11, which is connected to eight mooring lines by designed pre-tension. In this step, the
x-offset of the structure was largely reduced by four tugboats, and there was no difference in the behavior of the structure between Tugs 2 and 4. In the absence of a tugboat, the effect of the steady drift force was reduced significantly compared to Step 6, as shown in
Fig. 19, but the amplitude of the offset was increased.
Fig. 25 presents the results of frequency analysis, i.e., FFT (Fast Fourier transform), of the time history of surge motion and second-order wave force when the tension of eight mooring lines was set to the designed pre-tension. In this graph, the two peak frequencies almost coincided. As a result, a large amplitude of
x-offset occurred.
In the situation where two tugboats were arranged, the structure showed larger amplitudes in the y and θz directions than the other cases, but it was relatively stable compared to Step 6.
Figs. 26,
–
28 show the
x,
y, and
θz offset of the structure in Step 16, which is connected to 12 mooring lines by designed pre-tension. No significant differences in the offset of the structure were observed between Tugs 4 and 2. When the position is maintained only by the tension of the mooring line without a tugboat, the
y and
θz offset is extremely small. In the case of the
x-offset, the movement was reduced significantly compared to Step 11.
Figs. 29,
–
31 show the
x,
y, and
θz offset of the structure in Step 21, which is the final step in the hook-up procedure. When the entire mooring line was connected to the structure, the
x-offset behaves stably without connecting a tugboat (as shown in
Fig. 29). In addition, even in the
y and
θz offsets, the motion of the structure maintained a minute value without connecting a tugboat.
4.4 Results
The simulation results for the behavior of the structure during the hook-up installation derived in this study are represented using significant values (as shown in
Figs. 32,
–
34). The thick solid line indicates the final hook-up procedure. The structure, which arrived at the installation site by transportation, starts the hook-up installation by connecting the first mooring line while maintaining its position using four tugboats. When the step of connecting the 6th mooring line (Step 8) was over, the two tugboats were withdrawn, and the position of the structure was maintained until 12 mooring lines were connected with the remaining two tugboats (Step 16). In this way, by arranging only two tugboats, the structure can control large movements in the
x-direction, which occurred due to the second-order wave force in Step 11 (eight mooring lines are connected with designed pre-tension). All tugboats were withdrawn at Step 17, and installation was carried out until Step 21, which is a final step, while the structure maintains its position by only mooring lines.
Therefore, the significant value of the structure offset was set not to exceed 6 m when organizing the installation procedure by summarizing the simulation results according to the arrangement of the tugboat. Each classification society and certification body present only the external environmental conditions according to the installation period for mooring system installation. Moreover, there were no regulations during the installation process, such as stability and installation plans. Normally, during hook-up installation, all tugboats are withdrawn when half of the entire mooring line is connected. In the case of this study, however, at the stage of Step 11, when half of the mooring lines are connected, the structure exhibited large behavior due to the low-frequency motion. Therefore, the significant x-offset of the structure in Step 16, which is considered relatively stable, was adopted and used as a reference. In addition, after the four mooring lines were connected (Step 6), the structure did not exceed the reference value with only two tugs, but considering the steady drifting force and unstable motion of the structure in the y and θz direction, two tugboats were configured to withdraw after Step 8.